一、质量计划.doc
3、工程质量目标
(1)消除不合格工程,杜绝质量隐患;
(2)分项工程合格率100%,优良率达到90%以上;
(3)分部工程质量合格率100%,优良率达85%以上;
(4)单位工程竣工一次交验合格,观感得分率90%以上;
(5)结构确保长城杯,争创竣工鲁班奖。
4、施工组织
4.1施工组织系统
该工程采用项目负责制,为确保合同规定工程质量,公司经研究决定,由公司副总经理×××挂帅,并在公司内抽出业务水平、管理水平高、具有丰富施工经验的精干管理人员组成××大厦项目经理部承担工任务。
施工组织机构如下图所示:
4.2 职能分工及职责
4.2.1 项目部经理岗位职责
(1)对所承担的项目工程质量全面负责,组织贯彻国家和上级关于质量工作的方针政策、法规的落实。
(2)决定项目年度质量目标质量实施计划,主持质量工作会议,明确项目管理,执行验证等人员职责和权限。
(3)组织人力物力,资源活动,分析质量情况,采取收正措施和预防措施。
(4)负责本项目部接受质量体系审核的准备工作,参加管理评定。
4.2.2项目部生产副经理岗位职责
3, quality targets
(1) the elimination of substandard construction, to prevent quality risks;
(2) sub-projects 100% pass rate, good rate of more than 90%;
(3) Quality Division works 100% pass rate, good rate of more than 85%;
(4) units of project completion time for examination pass rate of 90% perception scores;
(5) structure to ensure that the Great Wall Cup, striving to be completed Luban.
4, construction organization
4.1 Construction organization system
The project by project responsibility, to ensure the quality of the project contract, the company was decided by the company's vice president of × × × in command, and the level of the company out of business, management of high level, with extensive experience in lean construction managers who × × Building Project Management Team undertake work tasks.
Construction of the organization as shown below:
4.2 The division of functions and duties
4.2.1 Project Manager Responsibilities
(1) assumed overall responsibility for quality of the projects, organizing and implementing national and superior quality of work on policies, laws and regulations implemented.
(2) determine the quality of the project implementation plan for the annual quality objectives, quality of work over the meeting, a clear project management, implementation and validation of responsibility and authority.
(3) organizations, resources, resources, activities, quality of analysis and adopt positive measures and preventive measures received.
(4) Department in charge of the project acceptable quality system audit preparation, participation in management evaluation.
4.2.2 Project Department Production Assistant Manager Responsibilities
帮助中心 收藏 >>> |
本类栏目导航
总点击排行
- 天正建筑2013最新64位破解版
- 173549次
- Autocad2013 64位32位破解版附带注册机
- 154872次
- 天正建筑8.5破解版
- 146385次
- autocad2012 64位32位 破解版(附注册
- 139021次
- 天正建筑8.2破解版
- 127265次
- autocad2010免费下载(简体中文版)
- 98144次
- 免费农村房屋设计图
- 90905次
- CAD2008注册机及使用说明
- 84340次
- 11g101图集全套下载
- 78882次
- cad图集大全
- 67445次
- 全套教学楼毕业设计
- 2515次
- 5号、4A号砖砌化粪池施工方案
- 2122次
- 施工围墙施工方案
- 1698次
- 后浇带施工方案
- 1486次
- 悬挑式脚手架施工方案
- 1412次
- 冬季施工应急预案
- 1215次
- 大型机械土石方平整工程施工方案
- 1204次
- 现场安全文明施工方案
- 1150次
- 悬挑卸料平台搭设方案及计算
- 1138次
- 楼梯踏步护角做法(CAD)
- 1111次