大面积高标准地坪原浆抹面施工工艺.doc
大面积高标准地坪原浆抹面施工技术
1、 施工准备
1.1、 认真编制施工技术措施,严格连续浇筑和逝世修整、机械抹平程度,作好人力物力综合平衡。
1.2、 组织技术措施学习和实施操作预演。
1.3、 选择经验丰富、责任心强的工人负责机械抹面的工作。
1.4、 机操工认真熟悉抹光机的机械性能并能进行养护和调试。
1.5、 加强监督、管理人员明确分工,做到每道工序、每班责任落实到人并层层把关。
2、 施工过程
2.1、标高控制
2.1.1、由柱网尺寸和业主对表面平整度的要求划分标高网点密度。
2.1.2、标高点的制作:用“螺标
Large area of high standards of floor puree finishing construction technology
1, construction preparation
1.1, carefully prepared construction techniques, rigorous continuous casting and the death of finishing, mechanical smoothing level, well integrated balance of human and material resources.
1.2, organizational learning and implementation of technical measures preview operation.
1.3, selection of experienced, responsible workers responsible for mechanical finishing work.
1.4, machine operating work seriously familiar with the trowel of the mechanical properties and to carry out maintenance and debugging.
1.5, and strengthen supervision and management personnel clear division of labor, so that each process, class responsibilities to people and checks at each level.
2, the construction process
2.1, elevation control
2.1.1, property owners from the column net size and surface roughness on the requirements of division level network density.
2.1.2, the production of elevation point: The "Lo standard