砖混结构(构造柱、圈梁、板缝等)砼浇筑
本技术交底适用于砖混结构,包括外砖内模和外板内模结构的构造柱、圈梁、板缝等现浇混凝土工程。
1.材料要求
(1)水泥;用325~425号矿渣硅酸盐水泥或普通硅酸盐水泥。
(2)砂:宜用粗砂或中砂。
(3)石子:构造柱、圈梁宜用粒径0.5~3.2厘米的卵石或碎石;板缝用粒径0.5~1.2厘米豆石或碎石。
(4)外加剂:根据要求选用早强剂和减水剂等。掺用时必须有试验依据。
2.作业条件
(1)混凝土配合比需经试验室确定,配合比通知单与现场使用材料相符。
(2)模板牢固、稳定,标高尺寸符合要求,模板缝隙最大不得超过2.5毫米,过大者应堵严,并办完预检手续。
(3)绑好钢筋并办完隐检手续。
(4)构造柱、圈梁及板缝施工缝接搓处的松散混凝土和砂浆,应剔凿清理并将模板内杂物清除干净。
(5)常温施工时,在混凝土浇灌前,砖墙、木模应提前适量浇水湿润,但不得有积水。
3.操作工艺
工艺流程
作业准备→混凝土搅拌→混凝土运输→混凝土浇灌、振捣→混凝土养护
(1)混凝土搅拌:
1)根据测定的砂石含水率调整配合比中的
Cards on the table Abstract:


Cards on the table contents:
Brick-concrete structure (structural columns, ring beams, seams, etc.) Pouring
The technical disclosure applies to brick and concrete structure, including the internal model and the outside brick mold structure within the outer structural column, ring beam, slab joint projects such as pouring concrete.
1. Material requirements
(1) cement; with 325 ~ 425 slag Portland cement or ordinary Portland cement.
(2) sand: coarse sand or the sand is preferred.
(3) stone: structural columns, ring beams and it is appropriate particle size of 0.5 to 3.2 cm gravel or crushed stone; seams with a diameter of 0.5 to 1.2 cm beans stone or gravel.
(4) Admixture: selected early strength agent, upon request, and water reducing agent. Must be mixed with a test basis.
2. Operating conditions
(1) concrete mix be determined by the laboratory, with the use of materials than the notice in line with the site.
(2) template solid, stable, and elevation measurements meet the requirements of the largest template shall not be more than 2.5 mm gap, were too strict to be blocked, and after finishing pre-screening procedures.
(3) Tie bar, and after finishing implicit review procedures.
(4) structural columns, ring beams and slab joint construction joint then twist Department of loose concrete and mortar, chisel should tick debris clean-up and cleaned within the template.
(5) at room temperature construction, before pouring the concrete, brick, wood mold should be moist before watering amount, but not with water.
3. Operation Process
Process:
Concrete mixing operation ready → → → concrete pouring of concrete transport, concrete curing vibrated →
(1) Concrete Mixing:
1) The adjustment of water content measured with the ratio of sand and gravel in
 