砖混、外砖内模结构钢筋绑扎
本技术交底适用于工业与民用建筑砖混结构、外砖内模结构的构造柱、圈梁、板缝钢筋绑扎工程。
1.材料要求
(1)钢筋出厂合格证和复试试验报告结论均要符合设计和规范要求。
(2)成型钢筋、20~22号火烧丝、水泥砂浆垫块(或塑料卡)。
2.主要机具
钢筋钩子、小撬棍、钢筋板子、绑扎架、钢丝刷、运钢筋手推车、粉笔、脚手架、工作台等。
3.作业条件
(1)按施工平面图规定的位置平整好场地,按不同规格型号垫好堆放。
(2)进场钢筋应对照设计图纸和配料单,详细核对其型号、尺寸、数量、钢号、对焊的接焊质量。
(3)弹好标高水平线及构造柱、外砖内模混凝土墙的外皮线。
(4)圈梁及板缝模板已做完预检记录,并将模内杂物清理干净。
(5)预制圆孔板的端孔已按标准图(京92G41)的要求堵好。
4.操作工艺
(1)构造柱钢筋绑扎:
工艺流程
预制构造柱钢筋骨架→修整底层伸出的构造柱搭接筋→安装构造柱钢筋骨架→绑扎搭接部位箍筋
1)预制构造柱钢筋骨架:
A.先将两根竖向受力筋平放在绑扎架上,画箍
Brick, brick internal model of foreign steel banding
The technical disclosure for industrial and civil construction brick, brick outer structural column within the model structure, ring beam, slab joint steel banding project.
1. Material requirements
(1) steel factory test certificate and re-testing to the report's conclusions are consistent with the design and specifications.
(2) reinforcement steel, 20 to 22 fire wire, cement mortar Pad (or plastic card).
2. Major equipment
Steel hook, small crowbars, steel board, lashing rack, wire brush, steel trolley transportation, chalk, scaffolding, working platforms and so on.
3. Operating conditions
(1) The location of the construction plan provides a good level site, according to different specifications and models good pad stack.
(2) approach control design drawings of reinforced and ingredients should be a single, detailed verification of its type, size, quantity, steel, butt welding quality of the access.
(3) good elevation level and structure elastic column, outside the brick wall of concrete inside the skin line.
(4) ring beam and slab joint template has been done pre-recorded, and mold clean up debris.
(5) pre-hole side plate hole has been the standard map (Beijing 92G41) the requirements of good blocking.
4. Operation Process
(1) structural steel columns Binding:
Process:
Prefabricated structural steel skeleton → pillar trim the bottom out of the structural column reinforcement lap steel skeleton structural column → install → stirrup position lap banding
1) prefabricated steel frame construction column:
A. First two vertical bars flat on the lashing force shelves, painted hoop
 