安装避雷装置的通知
为避免大型机械设备、建筑物遭受雷击损害,请各单位制作安装避雷装置。
一、避雷装置安装范围
1、龙门吊轨道、模板轨道、提梁机轨道;
2、塔吊、搅拌机、竖井提升机;
3、爆炸品料库;
4、所有轨道要连接到一起,保证轨道不断。如轨道断开,应采用连接线连接。
二、安装要求
1、避雷针采用φ25圆钢制作,其针尖须做成针式,并镀锡。
2、引下线采用φ12圆钢,连接线采用φ12圆钢或16-25mm2铝线/铜线。
3、引下导线的途径要尽量缩短,避免90º的弯折,引下导线及其固定装置要牢固地固定在建筑物上,固定装置的间距不能大于1.5m。
4、各种接头采用焊接,焊接困难时采用螺栓连接。连接要焊接牢固,不能开焊脱节。
5、接地体要选择在地势较低洼或经常潮湿的处所进行埋设。
6、埋入地下的金属导体须距离建筑物或门口3m以上。
7、接地体回填土前,须对接地电阻进行测定,接地电阻应不大于10Ω。
三、安装图
见附图《避雷、接地装置图》
Installation of lightning protection device notification
In order to avoid large-scale machinery and equipment, buildings being struck by lightning damage, please install lightning protection devices and units produced.
First, the scope of lightning protection devices installed
1, gantry crane track, the template track, Gantry Crane Rail;
2, tower cranes, mixers, elevator shaft;
3, explosives database;
4, all the tracks you want to connect together to ensure the track continuously. Such as the track off, should be used to connect cable.
Second, the installation requirements
1 lightning rod using φ25 round production, the needle tip to be made, and tin.
2, deflectors using φ12 round steel, round steel cable with φ12 or 16-25mm2 wire / copper wire.
3, lead the way under the wire should be as short as possible, to avoid the 90 º of bending, lead wires and fixtures under the firmly fixed to buildings, fixtures of the pitch can not be greater than 1.5m.
4, various joints welded, welding difficulties connected with bolts. Connected to welding firm, not out of line open welding.
5, the grounding to choose a more low-lying terrain is often wet or premises for burial.
6, the metal conductor to be buried in the ground or from the front of 3m above the building.
7, grounding backfill before, was determined to be of the grounding resistance, earth resistance should not be greater than 10Ω.
Third, the installation diagram
Please refer to "lightning, grounding device map"
帮助 收藏 报错 评论>> |
本类栏目导航
总点击排行
- 天正建筑2013最新64位破解版
- 160786次
- Autocad2013 64位32位破解版附带注册机
- 148386次
- 天正建筑8.5破解版
- 144084次
- autocad2012 64位32位 破解版(附注册
- 137477次
- 天正建筑8.2破解版
- 123425次
- autocad2010免费下载(简体中文版)
- 97157次
- CAD2008注册机及使用说明
- 80847次
- 免费农村房屋设计图
- 73856次
- cad图集大全
- 56939次
- 11g101图集全套下载
- 45666次
- 木工安全技术交底
- 984次
- 土方回填安全技术交底
- 957次
- 环境保护与水土保持措施
- 940次
- 钻孔灌注桩安全技术交底
- 805次
- 电焊、风割焊作业安全技术交底
- 723次
- 跨铁路工程施工安全防护措施补充方案
- 622次
- 安装避雷装置图
- 580次
- 钢筋工安全技术交底
- 557次
- 施工现场的临时照明.场内交通及水电设
- 510次
- 沥青路面沥青洒布机作业-水泥混凝土路
- 491次