杭州市德胜快速路工程防汛、防台应急预案.doc
防汛、防台应急预案
一、 编制目的
杭州市地处亚热带北缘,属亚热带季风气候,年平均温度为16.6℃,多年平均降雨量1399mm,一年有两个雨季,4~6月为梅雨季,强度不大,雨天连绵不断;7~9月为台风暴雨季,雨大集中,台风过境中心风力最高可达12级。
杭州市德胜快速路工程项目是杭州市城市重点建设项目之一。我项目部承建的跨铁路B1标工程,总工期为365天,工程量大而工期紧。梅雨、台风季节正好是我标段工程施工墩台、箱梁的季节。为了作好施工现场“防台防汛”工作,加强现场组织管理,认真落实抢险准备工作,以对付突发性自然灾害事故的发生,保护公共财产及人身安全,保证工程有序施工,特制定本应急预案。
二、 编制依据
根据《中华人民共和国安全生产法》、《建设项目环境保护管理条例》、《工程建设重大事故报告和调查程序规定》、《中华人民共和国防汛条例》细则和杭州市水文气象条件,认真贯彻以“预防为主,以消为辅”为指导思想,结合本工程实际情况,制定防汛、防台计划,并部署、落实好各施工项目的防汛、防台安全
Flood, typhoon emergency response plan
First, the preparation of purpose
Hangzhou is located in the subtropical north edge of subtropical monsoon climate, annual average temperature is 16.6 ℃, annual average rainfall of 1399mm, there are two rainy seasons a year, 4 to 6 months for the monsoon rains slightly, with rain continuously; 7 September is the rainy season sets storm, rain big concentration of wind typhoon center up to grade 12.
Desheng, Hangzhou, Hangzhou Expressway project is one of the key urban construction projects. I cross the railway construction project department B1 standard works, with a total duration of 365 days, projects large and short construction period. Plum rains, typhoon season is just my pier construction Lot, Box season. In order to prepare the construction site of "anti-Taiwan, flood control", and strengthen the organization and management field, conscientiously implement the emergency preparations to deal with unexpected natural disasters, accidents and protect public property and personal safety, ensure the orderly construction project is formulated emergency plan.
2, prepared on the basis
According to "Production Safety Law", "Construction Project Environmental Protection Management Regulations", "construction of major accident reporting and investigation procedures" and the "People's Republic of flood control regulations," Rules and Hangzhou hydrological and meteorological conditions, conscientiously implement the " prevention, in order to eliminate secondary "as the guiding ideology, combining the actual situation of the project to develop flood control, anti-Taiwan program, and deploy, and implement the construction of flood control projects, anti-Taiwan security
帮助 收藏 报错 评论>> |
本类栏目导航
总点击排行
- 天正建筑2013最新64位破解版
- 160786次
- Autocad2013 64位32位破解版附带注册机
- 148386次
- 天正建筑8.5破解版
- 144084次
- autocad2012 64位32位 破解版(附注册
- 137477次
- 天正建筑8.2破解版
- 123425次
- autocad2010免费下载(简体中文版)
- 97157次
- CAD2008注册机及使用说明
- 80847次
- 免费农村房屋设计图
- 73857次
- cad图集大全
- 56939次
- 11g101图集全套下载
- 45667次
- 木工安全技术交底
- 984次
- 土方回填安全技术交底
- 957次
- 环境保护与水土保持措施
- 940次
- 钻孔灌注桩安全技术交底
- 805次
- 电焊、风割焊作业安全技术交底
- 723次
- 跨铁路工程施工安全防护措施补充方案
- 622次
- 安装避雷装置图
- 580次
- 钢筋工安全技术交底
- 557次
- 施工现场的临时照明.场内交通及水电设
- 510次
- 沥青路面沥青洒布机作业-水泥混凝土路
- 491次