京珠高速公路广珠北15标粉喷桩安全技术交底.doc
1、搅拌桩机进场后,作业人员必须戴安全帽,机长安排人员装机、竖支架、布设临时用电,做到安全合理;
2、搅拌桩机按要求就位后,由安全股、机材股联合进行一次全面的施工前安全检查。检查内容有:用电安全、桩架的稳定性,操作部位的性能,导向部件的稳固程度等,确保安全符合要求后才准予施工;
3、每次施工前,由施工员负责对搅拌机进行安全检查,不符合安全要求的禁止强行施工;
4、必须配有专门的电工,持证上岗;
5、操作手必须经过专业培训,熟练掌握搅拌桩机施工操作规程;
6、所有用电开关必须有保险装置,禁止用铜丝或其它导体代替专用保险丝,所用电缆线必须完好不破损,不漏电,接头部位必须包扎好,用干燥的绝缘物支架起来;
7、负责送料的作业人员必须戴好安全帽,施工过程中不能站在搅拌机底下,以预防落物伤人;高空作业,必须系好安全带;
8、送料人员应在远离桩机范围,随时注意桩机及周围环境变化,防止意外;
9、在移动过程中,保证桩机的整体平衡,小
1, mixing pile driver approach, the operating personnel must wear a helmet, captain arrange machines, vertical stand, laying temporary electric, so that reasonable and safe;
2, mixing pile driver in place as required, by the security unit, machine materials stocks a comprehensive joint safety inspection before construction. Check the contents of: electrical safety, the stability of pile frame, the operation part of the performance-oriented parts of the stability, to ensure safety to meet the requirements before construction grant;
3, each pre-construction, construction workers from the mixer is responsible for safety checks, do not meet safety requirements prohibit forced construction;
4, must be equipped with special electrical, certificates;
5, operator must be trained, master mixing pile driver construction practices;
6, all power switches must have a safety mechanism to prohibit the use of copper wire or other conductor to replace dedicated fuse, the power cable must be intact not broken, do not leak, joints must be wrapped with insulation and dry up support;
7, is responsible for feeding operations must wear a helmet, the construction process can not under stand mixer, to prevent litter wounding; aerial work, you must fasten your seat belts;
8, feed away from the pile driver in the scope of staff should, at any time pay attention to changes in pile driver and the surrounding environment to prevent accidents;
9, during the moving process to ensure overall balance pile driver, small
帮助 收藏 报错 评论>> |
本类栏目导航
总点击排行
- 天正建筑2013最新64位破解版
- 160786次
- Autocad2013 64位32位破解版附带注册机
- 148386次
- 天正建筑8.5破解版
- 144084次
- autocad2012 64位32位 破解版(附注册
- 137477次
- 天正建筑8.2破解版
- 123425次
- autocad2010免费下载(简体中文版)
- 97157次
- CAD2008注册机及使用说明
- 80847次
- 免费农村房屋设计图
- 73857次
- cad图集大全
- 56939次
- 11g101图集全套下载
- 45667次
- 木工安全技术交底
- 984次
- 土方回填安全技术交底
- 957次
- 环境保护与水土保持措施
- 940次
- 钻孔灌注桩安全技术交底
- 805次
- 电焊、风割焊作业安全技术交底
- 723次
- 跨铁路工程施工安全防护措施补充方案
- 622次
- 安装避雷装置图
- 580次
- 钢筋工安全技术交底
- 557次
- 施工现场的临时照明.场内交通及水电设
- 510次
- 沥青路面沥青洒布机作业-水泥混凝土路
- 491次