扇灰班施工质量安全技术交底.doc
扇灰班施工质量安全技术交底
1、 凡进入施工区内工作、必须戴好安全帽及胸卡,不准穿拖鞋上班,不准穿短裤、光身子、衣服要扣好,做到文明施工。
2、 严禁在同一工作部位上下同时工作,进入吊笼时要待吊笼停稳,并不准将身体探入吊笼内,以免造成意外。
3、 施工用桥架必须扎牢,必须用两个门式架加斜撑并排扎稳,形成较大的操作空间,平台板要安全可靠,两头伸出不少于10公分,四周要做好护栏。
4、 扇灰所用胶体,必须严格按照设计配合比进行配料。
5、 施工前必须对各部位提前一到两天用水冲洗干净表面灰尘及各种杂物,以免造成隔层。
对于施工部位表面上的铁钉、铁丝必须用砂
Plaster construction quality and safety technical disclosure class
1, where the work into the construction area must wear safety helmets and badges, are not allowed to wear slippers to work, not allowed to wear shorts, light body, clothes to be held in place in a civilized construction.
2, upper and lower parts of the work is prohibited in the same work simultaneously to enter the cage when the cage to be a parked, does not probe into the lifting body Brigadier cage, so as to avoid accidents.
3, with the bridge construction to fasten, two-door frame must be braced side by side bar stability, leading to higher operating room, the platform board to be safe, reliable, two out of no less than 10 cm, 4 weeks to do a good job fence.
4, plaster used in gel must be carried out strictly in accordance with the design mix ingredients.
5, before the construction of various parts of one to two days ahead of the surface water rinse dust and all kinds of debris to avoid compartment.
For the construction site on the surface of nails, wire must be sand
帮助 收藏 报错 评论>> |
本类栏目导航
总点击排行
- 天正建筑2013最新64位破解版
- 160786次
- Autocad2013 64位32位破解版附带注册机
- 148386次
- 天正建筑8.5破解版
- 144084次
- autocad2012 64位32位 破解版(附注册
- 137477次
- 天正建筑8.2破解版
- 123425次
- autocad2010免费下载(简体中文版)
- 97157次
- CAD2008注册机及使用说明
- 80847次
- 免费农村房屋设计图
- 73857次
- cad图集大全
- 56939次
- 11g101图集全套下载
- 45668次
- 木工安全技术交底
- 984次
- 土方回填安全技术交底
- 957次
- 环境保护与水土保持措施
- 940次
- 钻孔灌注桩安全技术交底
- 805次
- 电焊、风割焊作业安全技术交底
- 723次
- 跨铁路工程施工安全防护措施补充方案
- 622次
- 安装避雷装置图
- 580次
- 钢筋工安全技术交底
- 557次
- 施工现场的临时照明.场内交通及水电设
- 510次
- 沥青路面沥青洒布机作业-水泥混凝土路
- 491次