施工前准备施工测量.施工现场的临时照明施工安全技术交底.doc
交底内容 施工所用的各种机具设备和劳动保护用品,应定期进行检查和必要的检验,保证其经常处于完好状态;不合格的机具设备和劳动保护用品严禁使用。下挖工程,施工前应根据设计文件复查地下构造物(电缆、管道等)和埋置及走向,并采取防护措;施工中如发现有危险品及其它可疑物品时,应即停止下挖,报请有关部门处理。重要的安全设施必须执行与主体工程“三同时”的原则,即:同时设计、审批,同时施工,同时验收,投入使用。
施工前准备
施工现场 施工现场应有利于生产,方便职工生活,符合防洪、防火等安全要求,具备文明生产、文明施工的条件 。施工现场的临时设施,必须避开泥沼、悬崖、陡坡、泥石流、雪崩等危险区域,先在水文、地质良好的地段。施工现场内的各种运输道路、生产生活房屋易燃易爆仓库、材料堆放,以及动力通讯线路和其它临时工程,应按照有关安全的规定制定出合理的平面布置图。 施工现场的生活生产房屋、变电所、发电机房、临时油库等均应设在干燥地基上,并应符合防火、防洪、防风、防爆、防震的要求。施工现场应设置安全标志,并不得擅自拆除。施工现场内的沟、坑、水塘等边缘应设安全护栏。场地狭小,行人运输繁忙的路段应设专门人指挥交通。生产生活房屋应按防火规定保持必需的安全净距,一般情况下活动板房不小于7m,铁皮板房不小于5m,临时的锅炉房、发电机房、变电室、铁工房、厨房等与其它房屋的间距不小于15m。
易燃易爆品仓库、发电机房、变电所,应采取必要的安全防护措施,严禁用易燃材料修建。炸药库的设置应符合国家有关规定,工地的小型临时油库的设置应符合国家有关规定。工地的小型临时油库应远离生活区50m以外,并外设围栏。工地上较高的建(构)筑物、临时设施及重要库房,如炸药库、油库、发(变)电房、塔架、龙门吊架等,均应加设避雷装置。对环境有污染的设施和材料应设置在远离人员居住的较为空旷的地点。污
Clarification at the contents of the various equipment used in construction equipment and labor protection products should be regularly checked and necessary checks to ensure its always in good condition; failure of machinery equipment and labor protection products is strictly prohibited. Under excavation, construction design documents shall be reviewed prior to underground structures (cables, pipes, etc.) and embedded and go, and take protective measures; construction is found to have dangerous goods and other suspicious items, they should stop digging under, reported to the relevant departments. Important safety facilities must be implemented with the main project of the "three simultaneous" principle, namely: while the design, approval, constructed, checked and accepted, put into use.
Pre-Construction
Construction site construction site should be conducive to production, to facilitate the livelihood of employees, consistent with flood control, fire and other safety requirements, have civilized production, the conditions of civilized construction. Construction site of the temporary facilities, to avoid the mud, cliffs, steep slopes, landslides, avalanches and other dangerous areas, first in hydrology, geology a good location. Construction site, all within the road transport, production and living housing flammable storage, material stacking, and dynamic communication lines and other temporary works, should be developed in accordance with the relevant safety requirements at a reasonable floor plan. Production life of the construction site housing, transformer substation, generator room, temporary storage facilities, should be located in a dry foundation, and should meet fire, flood, wind, explosion, earthquake requirements. Construction site safety signs should be set, and not allowed to remove. Within the construction site trench, pits, reservoirs and other edge should be a safety barrier. Space narrow, busy pedestrian road transport specialist who should be set to direct traffic. Production and living housing should be provided to maintain the necessary fire safety clearance, under normal circumstances activities board room of not less than 7m, iron board room of not less than 5m, a temporary boiler room, generator room, transformer room, blacksmith room, kitchen, etc. and other housing space not less than 15m.
Flammable and explosive materials storage, generator room, transformer substation, shall take the necessary security measures, the construction of flammable material is strictly prohibited. Explosives library installation complies with state regulations, site of a small temporary tank set should be consistent with relevant state regulations. Small temporary depot site should be 50m away from the living area outside and peripheral fence. Construction site on the higher (structures), the Treasury temporary facilities and important, such as depots, depot, hair (variable) electrical room, tower, gantry, etc., shall be additional lightning protection devices. The environment and polluting facilities and materials should be set relatively far away from the officers open the site live. Polluted
帮助 收藏 报错 评论>> |
本类栏目导航
总点击排行
- 天正建筑2013最新64位破解版
- 160786次
- Autocad2013 64位32位破解版附带注册机
- 148386次
- 天正建筑8.5破解版
- 144084次
- autocad2012 64位32位 破解版(附注册
- 137477次
- 天正建筑8.2破解版
- 123425次
- autocad2010免费下载(简体中文版)
- 97157次
- CAD2008注册机及使用说明
- 80847次
- 免费农村房屋设计图
- 73857次
- cad图集大全
- 56939次
- 11g101图集全套下载
- 45668次
- 木工安全技术交底
- 984次
- 土方回填安全技术交底
- 957次
- 环境保护与水土保持措施
- 940次
- 钻孔灌注桩安全技术交底
- 805次
- 电焊、风割焊作业安全技术交底
- 723次
- 跨铁路工程施工安全防护措施补充方案
- 622次
- 安装避雷装置图
- 580次
- 钢筋工安全技术交底
- 557次
- 施工现场的临时照明.场内交通及水电设
- 510次
- 沥青路面沥青洒布机作业-水泥混凝土路
- 491次