铁器构件安装工程安全作业交底.doc
内容摘要:
1、 吊运工作时,应注意被吊工作物的重量及使用钢丝绳(千斤绳)的允许荷载力,并向吊机指挥人员说明吊物的目的地,并事先清理目的地周围的障碍物。
2、 吊装工作就位时,应注意安装人员的手和脚,要做到稳、准。
3、 高空安装工件时,要戴好安全带、扣好保险扣,工件高空就位后要有临时固定措施,各类工具、材料、配件应采取防止高处坠落的安全措施。
4、 使用各类移动电具(如电钻、电板手、手提砂轮等)的电源插头必须实施二级漏电保护。
5、 铁器构件安装中的电焊、气割工作,应由有证的焊工进行,并办理现场动火审批手续,配有专职人员进行现场消防监护。
6、 使用铁锤前,应检查手柄牢固状况,敲打时不准戴手套。
7、 使用油泵千斤顶要注意压力负荷,要垫平放直。
8、 使用撬棒要注意放稳和力的支点,防止滑脱,弹击伤人,多人操作时要注意齐心协调。
9、严禁操作人员在酒后进入施工现场作业。
10、每个工人进入施工现场都必须头戴安全帽。
11、班组如果因劳力不足需要再招新工人时,应事先向工地报告。
12、新工人进场后应先经过三级安全交底,并经考试合格后方可让其正式上岗。
13、新工人进场应具有四证,即:职业资质证、身份证、计划生育证和外来人口暂住证。
Abstract:
1, lifting work, should pay attention to the weight of objects suspended from work and the use of wire rope (extremely heavy rope) and allow the load force commanders instructions to the crane hoist the destination and destinations around the obstacle clearance in advance.
2, lifting the work place, attention should be installed on staff hands and feet, to be sure, accurate.
3, workpiece height when installed, to wear your seat belt fastened the insurance deduction, after the workpiece should be temporary fixed height measures in place, all kinds of tools, materials, accessories should take safety measures to prevent falling from height.
4, using various types of mobile electronic devices (such as drills, power wrenches, hand wheel, etc.) need to implement two power plug leakage protection.
5, iron components installed in the welding, gas cutting work should be of certified welders, and go through the on-site hot work procedures for approval, with a full-time staff on-site fire monitoring.
6, use the hammer, should check the status of the handle firmly, tap the time allowed to wear gloves.
7, using the oil pump jack should pay attention to pressure overload, to pad flat straight.
8, using the pry bar to pay attention to put the fulcrum of stability and strength to prevent slippage, playing the wounded people, people pay attention to work together to coordinate operations.
9, is strictly prohibited operators in the drink to the construction site work.
10, each worker entering the construction site must be wearing helmets.
11 team if the need to move because of a labor shortage of new workers, the report shall be submitted to the site.
12, after the admission of new workers should go through three security correspondent, and pass the examination before they can let the official posts.
13, the new approach should have four cards of workers, namely: professional qualification certificate, identity cards, birth certificates and residence permits.
帮助 收藏 报错 评论>> |
本类栏目导航
总点击排行
- 天正建筑2013最新64位破解版
- 160786次
- Autocad2013 64位32位破解版附带注册机
- 148386次
- 天正建筑8.5破解版
- 144084次
- autocad2012 64位32位 破解版(附注册
- 137477次
- 天正建筑8.2破解版
- 123425次
- autocad2010免费下载(简体中文版)
- 97157次
- CAD2008注册机及使用说明
- 80847次
- 免费农村房屋设计图
- 73857次
- cad图集大全
- 56939次
- 11g101图集全套下载
- 45668次
- 木工安全技术交底
- 984次
- 土方回填安全技术交底
- 957次
- 环境保护与水土保持措施
- 940次
- 钻孔灌注桩安全技术交底
- 805次
- 电焊、风割焊作业安全技术交底
- 723次
- 跨铁路工程施工安全防护措施补充方案
- 622次
- 安装避雷装置图
- 580次
- 钢筋工安全技术交底
- 557次
- 施工现场的临时照明.场内交通及水电设
- 510次
- 沥青路面沥青洒布机作业-水泥混凝土路
- 491次