竹脚手架拆除工程安全作业交底.doc
内容摘要:
1、 凡不符合高处作业的人员,禁止登高作业。并严禁酒后高处作业。
2、 严格正确使用劳动保护用品。遵守高处作业规定,工具必须入袋,物件严禁高处抛掷。
3、 强风区、雪天区、雨天区的环境,不准时行拆除作业。
4、 夜间拆除,必须布置良好的照明设备。
5、 拆除区或须设置警戒范围,设立明显的警示标记,非操作人员或地面施工人员,均不得通行或施工,安全员应配合现场监护。
6、 高层脚手架的拆除,应配备通讯装置。
7、 拆除物件,应有垂直运输机械安全输送至地面,吊机不允许设在脚手架内。
8、 施工前应仔细检查各结点、攀桩、传动、索具等是否可靠,杆件必须二点捆扎吊运。
9、 拆除时,建筑内应及时关闭窗户,严禁向窗外伸挑任何物件。
10、高层脚手架拆除,应沿建筑四周一步一步递减。不允许二步同时拆除,或一前一后踏步式拆除,也不宜分立面拆除。如遇特殊情况,应有企业有关部门预先制定技术方案,经加固措施后,方可分立面拆除。
11、作业人员进入岗位后,应先进行检查,如遇薄弱环节时,应先加固后拆除。对表面存留的物件,垃圾应先清理。
12、按下列顺序进行拆除工作:安全网→挡笆→垫铺笆→防护栏杆→挡脚杆→搁栅→斜拉杆→连墙杆→横杆→顶撑→立杆。
13、立杆、斜拉杆的接长杆拆除,应二人以上配合进行,不宜单独作业,否则易引起事故。
14、连墙杆、斜拉杆、登高设施的拆除,应随脚手架整体
Abstract:
1, which do not meet the high operation, the prohibition of climbing operations. And non-work drink and height.
2, strictly correct use of labor protection articles. Comply with height job requirements, tools must be into the bag, thrown objects height is strictly prohibited.
3, strong wind area, snow area, wet area of the environment, when the lines are not allowed to demolition.
4, removed at night, good lighting to be arranged.
5, removal of area or areas shall be alert, warning marking the establishment of clear, non-operators or ground construction workers are not allowed to access or construction, with on-site security staff should be monitoring.
6, high-level scaffolding removed, should be equipped with communication devices.
7, removal of objects, should be perpendicular to the ground safe transport transport machinery, cranes are not allowed inside in scaffolding.
8, before the construction should be carefully examined each node, climbing poles, transmission, rigging and other reliability, two points must be tied bar lifting.
9, removal of, the building should be promptly closed the window, non-stretch to pick anything out the window.
10, high-level scaffolding removed, should be reduced step by step along the perimeter. At the same time does not allow two-step removed, or one after the other stepping-style demolition, should not be discrete surface removal. Under special circumstances, the relevant departments should be pre-established enterprise technology solutions, by strengthening the measures only after the removal of discrete surfaces.
11, operations officer to enter post, should first check, in case of weak links should be removed after the first reinforcement. Retention on the surface of objects, the garbage should be cleared first.
12, according to the following order removal of work: safety net block fence → → → protective pad shop fence railing foot pole → joists block → → → Wall oblique rod → rod → rod → top of support pole.
13, pole, pole removal of the access ramp rod should be carried out with two or more persons, not a separate operation, otherwise easily lead to accidents.
14, with walls, diagonal bar, climbing facilities shall be removed only with the overall scaffolding
帮助 收藏 报错 评论>> |
本类栏目导航
总点击排行
- 天正建筑2013最新64位破解版
- 160786次
- Autocad2013 64位32位破解版附带注册机
- 148386次
- 天正建筑8.5破解版
- 144084次
- autocad2012 64位32位 破解版(附注册
- 137477次
- 天正建筑8.2破解版
- 123425次
- autocad2010免费下载(简体中文版)
- 97157次
- CAD2008注册机及使用说明
- 80847次
- 免费农村房屋设计图
- 73857次
- cad图集大全
- 56939次
- 11g101图集全套下载
- 45668次
- 木工安全技术交底
- 984次
- 土方回填安全技术交底
- 957次
- 环境保护与水土保持措施
- 940次
- 钻孔灌注桩安全技术交底
- 805次
- 电焊、风割焊作业安全技术交底
- 723次
- 跨铁路工程施工安全防护措施补充方案
- 622次
- 安装避雷装置图
- 580次
- 钢筋工安全技术交底
- 557次
- 施工现场的临时照明.场内交通及水电设
- 510次
- 沥青路面沥青洒布机作业-水泥混凝土路
- 491次