S236伊山至六塘段养护改善工程标.doc
S236养护改善工程LJ1标近期工作计划
指挥部监理组:
由于河趟方案未定及K10+120—K10+340高填土路段,桥梁方案未定,土方缺口较大已没有土方施工,故暂不考虑此路段施工,现将我标段近期工作安排如下:
4.11—4.17完成: K10+340—K10+540 12%灰土右侧调平270M3。
K10+240—K10+340 6%灰灰土处理140M3。
18—25完成: K10+340—K10+540 12%灰土左侧顶层200 M3。
K10+540—K10+900 12%灰土右侧顶层480 M3。
4.26—5.2完成: K10+340—K10+540 12%灰土右侧顶层270 M3。
K10+900—K11+240 12%灰土右侧顶层460 M3。
5月3号铲除K10+540—K11+240左侧覆盖土,
共计需完成工程量为 12% 1700M3
6% 140M3
土路肩600 M3
S236 recent conservation works LJ1 standard work plan
Command Management Group:
As the river trip programs and K10 +120- K10 +340 undecided high fill sections, the bridge program yet, no large gaps in earthwork earthwork construction, so temporarily consider the construction of this road is now to my recent work tenders as follows:
4.11-4.17 completed: K10 +340- K10 +540 12% dust-right leveling 270M3.
K10 +240- K10 +340 6% the dusty soil treatment 140M3.
18-25 to complete: K10 +340- K10 +540 12% lime on the left top 200 M3.
K10 +540- K10 +900 12% dust-right of the top 480 M3.
4.26-5.2 completed: K10 +340- K10 +540 12% dust-right of the top 270 M3.
K10 +900- K11 +240 12% dust-right of the top 460 M3.
May 3 K10 +540- K11 +240 left side of the Eradication of soil cover,
Total amount required to complete the project 12% 1700M3
6% 140M3
Soil shoulder 600 M3