浆喷桩技术交底.doc
交底内容:
1. 本处理地段搅拌桩桩径Ф500mm(搅拌钻头不小于Ф500mm)。采用42.5级普通硅酸盐水泥。每加固1m土体掺入水泥量为55kg,单位桩长水泥用量的负值偏差应控制在8%以内,单桩水泥用量负值偏差应控制在5%以内。
2. 采用两喷四搅法施工,自上而下搅拌,自下而上喷浆搅拌,水灰比为0.5。搅拌头上提喷浆时的提升速度为0.5~1m/min。浆喷桩应穿过软土层,并进入砂层或粘土层0.5米以上,当软土层超过18米,桩长按18米控制。
3. 测放桩位按设计要求进行,在确定孔位时,需经复核确认后方可进入下一施工工序,为保证桩位的准确性,桩位必须打入木桩或插入竹片作为桩位标记。
下钻杆时,先使桩机安置在标定的孔位上,使钻头中心对准孔中心,杆位偏差在±5cm以内,调整桩机水平度及垂直度,保证孔斜率不大于1.5%,终孔后校正钻具,桩径偏差不得大于4
Cards on the table contents:
1. The processing site mixing pile diameter Ф500mm (mixing drill not less than Ф500mm). With 42.5 ordinary portland cement. Strengthening 1m per volume of soil mixed with cement 55kg, unit pile length of the negative deviation of cement content should be controlled within 8%, a negative deviation of single pile of cement consumption should be controlled within 5%.
2. Using two four-jet mixing method construction, top-down mixing, spray mixing bottom-up, water cement ratio of 0.5. Spray mixing head to mention the improvement when the rate of 0.5 ~ 1m/min. Plasma jet should be through the soft soil pile and into the sand or clay layer 0.5 m above, when the soft soil layer more than 18 m, pile length by 18 meters control.
3. Measuring Pile up by design requirements, in determining the hole, the need to be confirmed by the review into the next construction process, in order to ensure the accuracy of the Pile, Pile must be inserted into the stakes or bamboo as the pile bit tag.
Under the drill, the first to pile driver placed in the calibration of the holes, so that the drill center hole aligned center pole position deviation within ± 5cm to adjust the level of degree and verticality of pile driver, to ensure hole is not more than 1.5% slope finally, after correction drill hole, pile diameter deviation of not more than 4
帮助 收藏 报错 评论>> |
本类栏目导航
总点击排行
- 天正建筑2013最新64位破解版
- 160514次
- Autocad2013 64位32位破解版附带注册机
- 148307次
- 天正建筑8.5破解版
- 144041次
- autocad2012 64位32位 破解版(附注册
- 137474次
- 天正建筑8.2破解版
- 123392次
- autocad2010免费下载(简体中文版)
- 97140次
- CAD2008注册机及使用说明
- 80806次
- 免费农村房屋设计图
- 73715次
- cad图集大全
- 56756次
- 11g101图集全套下载
- 45286次
- 路缘石安装技术交底记录
- 1374次
- 施工组织设计交底记录
- 1155次
- 公路施工安全技术交底
- 1047次
- 检查井施工技术交底
- 868次
- 土石方开挖施工技术交底记录
- 829次
- 排水工程雨水管施工技术交底
- 757次
- 边沟盖板安装施工技术交底记录
- 756次
- 雨水管道安装技术交底记录
- 719次
- 墩柱施工技术交底
- 668次
- 综合管沟沟槽开挖、回填施工技术交底
- 609次