袋装砂井技术交底.doc
交底内容:
1、 本工程袋装砂井施工部位为非机动车道、人行道、绿化带和边坡,井径为7cm,其施工间距为1米,正方形布置,具体按照技术部门绘制的布桩图进行布置。
2、 施工机械为导管式振动打桩机;砂袋用聚丙烯编织袋;砂采用渗水率较高的中、粗砂,含泥量不应大于3%。
3、 施工工艺流程如下:
(1)整平原地面(2)摊铺20cm砂垫层(3)测量放线:用小木桩定出每个桩位,测出砂垫层面高程(4)机具对准桩位(5)打入套管(6)沉入砂袋(7)拔出套管(8)埋砂袋头
4、 质量要求:
(1) 允许偏差
Cards on the table contents:
1, the construction of Sand Wick Road construction sites for non-motor vehicles, sidewalks, green belts, and slope, well diameter of 7cm, the construction of distance is 1 meter square layout, specific technology sectors in accordance with plans drawn to pile layout.
2, construction machinery, pipe vibration pile driver; sand bags PP woven bags; sand with water seepage rates are relatively high, the coarse sand, mud content should not exceed 3%.
3, the construction process is as follows:
(1) The whole plain surface (2) Paving 20cm sand cushion (3) measurement and setting: using small wooden blocks set each pile location, measure the level sand pad elevation (4) Pile Alignment equipment (5) into the casing (6) sinking sand bags (7) pull the tube (8) head buried in sand bags
4, quality requirements:
(1) Tolerance
帮助 收藏 报错 评论>> |
本类栏目导航
总点击排行
- 天正建筑2013最新64位破解版
- 160514次
- Autocad2013 64位32位破解版附带注册机
- 148307次
- 天正建筑8.5破解版
- 144041次
- autocad2012 64位32位 破解版(附注册
- 137474次
- 天正建筑8.2破解版
- 123392次
- autocad2010免费下载(简体中文版)
- 97140次
- CAD2008注册机及使用说明
- 80806次
- 免费农村房屋设计图
- 73715次
- cad图集大全
- 56756次
- 11g101图集全套下载
- 45286次
- 路缘石安装技术交底记录
- 1374次
- 施工组织设计交底记录
- 1155次
- 公路施工安全技术交底
- 1047次
- 检查井施工技术交底
- 868次
- 土石方开挖施工技术交底记录
- 829次
- 排水工程雨水管施工技术交底
- 757次
- 边沟盖板安装施工技术交底记录
- 756次
- 雨水管道安装技术交底记录
- 719次
- 墩柱施工技术交底
- 668次
- 综合管沟沟槽开挖、回填施工技术交底
- 609次