侧平石技术交底记录.doc
交底内容:
1. 本工程道路侧平石是按照道路侧平石大样图(图号为D-15施)进行施工。
2. 本工程道路侧平石使用材料是:包括人行道侧石及绿化带侧石,人行道侧石规格为100×35×15cm,绿化带侧石100×15×30cm;平石规格为100×25×12cm。
3. 测量放线:
(1) 本工程侧平石利用6%水泥石屑稳定层施工中两侧自然宽出的多余部分作为基础垫层。
(2) 路面中线校核后,在路面边缘与侧平石交界处放出侧平石线,直线部位10m一桩,曲线部位5~10m,路口及分隔带、安全岛等圆弧,1~5m也可用皮尺画圆并在桩上标明侧平石顶面标高。
4. 刨槽:
按桩的位置打白灰线,以线为准,按设计要求宽度向外刨槽。靠近路面一侧,比线位宽出少许,一般不大于5cm。刨槽深度可比设计加深1~2cm,以保证基础厚度,槽底要
Cards on the table contents:
1. This project is in accordance with road side road side flat rock flat rock bulk sample (Figure No. D-15 facilities) for construction.
2. The project road side of the flat stone used materials include: sidewalk side of the stone and green with side stones, sidewalk side of the stone size is 100 × 35 × 15cm, green with a side of stone 100 × 15 × 30cm; square stone size was 100 × 25 × 12cm .
3. Measure for:
(1) The engineering side of the flat stone with 6% cement stabilization layer of stone chips on both sides of the construction of the excess part of the natural width of a cushion as a basis.
(2) After checking the road center line, edge and side of the road flat stone at the junction of the side flat stone line release, a 10m straight line position, the curve part 5 ~ 10m, road junctions and medians, pedestrian refuges arc, 1 ~ 5m tape can also be used Pile on a circle marked in the top side of flat stone elevation.
4. Routers:
Position by playing white ash pile line to line as, by design width of the outside router. Near the road side, than the line out a little bit wide, generally not more than 5cm. Router design better than the depth of 1 ~ 2cm, to ensure that the basis of thickness, bottom to
帮助 收藏 报错 评论>> |
本类栏目导航
总点击排行
- 天正建筑2013最新64位破解版
- 160514次
- Autocad2013 64位32位破解版附带注册机
- 148307次
- 天正建筑8.5破解版
- 144041次
- autocad2012 64位32位 破解版(附注册
- 137474次
- 天正建筑8.2破解版
- 123392次
- autocad2010免费下载(简体中文版)
- 97140次
- CAD2008注册机及使用说明
- 80806次
- 免费农村房屋设计图
- 73715次
- cad图集大全
- 56756次
- 11g101图集全套下载
- 45286次
- 路缘石安装技术交底记录
- 1374次
- 施工组织设计交底记录
- 1155次
- 公路施工安全技术交底
- 1047次
- 检查井施工技术交底
- 868次
- 土石方开挖施工技术交底记录
- 829次
- 排水工程雨水管施工技术交底
- 757次
- 边沟盖板安装施工技术交底记录
- 756次
- 雨水管道安装技术交底记录
- 719次
- 墩柱施工技术交底
- 668次
- 综合管沟沟槽开挖、回填施工技术交底
- 609次