交底内容:
1、边沟台帽养护期结束,砼强度达到设计强度的70%后,即可进行盖板的安装。
2、盖板采用场外预制,运输车运至现场吊装就位。
3、盖板吊装前,应将台帽顶清理干净,并提前放线确定每块板的位置,人孔井的位置尤其应标注准确。盖板吊装前,应于台帽上铺二毡三油支座,厚度2cm。
4、吊装采用25t汽车吊进行,应将台帽上预留的锚栓筋套入盖板锚栓孔内,注意不得将锚栓碰弯,相邻两块板应对接共用一根锚栓。
5、检查井盖板吊装时,应将井孔放于沟北侧,两块盖板组成一个检查井孔。
6、盖板安装安全注意事项:
(1)、盖板安装前,应检查盖板的吊环是否牢固,有无断裂现象。
(2)、盖板吊装前,钢丝绳应连接牢固。
(3)、盖板吊起后,人员严禁站在盖板及吊车吊臂下,以防发生意外。
7、盖板安装允许偏差:
      顺桥纵轴线方向      10mm
      垂直桥纵轴线方向    5mm
      
       
Cards on the table contents:
1, ditches Taiwan cap maintenance period is over, the design strength of concrete strength was 70%, you can to cover the installation.
2, cover with off-site prefabricated, transported to the site hoisting truck.
3, cover before lifting should be criminal to clean up Taiwan, and early pay-off to determine the location of each plate, one hole in particular, should mark the location of wells and accurate. Cover lifting, should be capped with two felt hats in Taiwan, three oil bearing, the thickness of 2cm.
4, 25t mobile crane used for hoisting, the cap should be reserved for Taiwan bars set into the cover bolt anchor bolt hole, pay attention to not touch the anchor bend, adjacent to the two boards should then share a bolt.
5, plate lifting manhole covers, the borehole should be placed in the north ditch, two Manhole cover up a hole.
6, cover installation of the safety precautions:
(1), cover before installation, check the cover of the rings are solid, with or without breaking.
(2), before lifting cover, wire should be connected firmly.
(3), cover lift, the staff is strictly prohibited and the cable car crane standing under cover, to prevent accidents.
7, cover installation tolerances:
      Vertical line along the direction of the bridge 10mm
      The vertical axis line direction of the bridge 5mm 
       
        
 