地下连续墙施工质量技术交底.doc
冲桩班防止偏孔质量技术交底内容:
根据造成偏孔的原因,在施工过程中采取以下防止措施:
1、根据甲方所提供的地质资料和相邻的槽孔的地质情况,及时予知进入岩层的深度、夹层情况以及岩面的坡度,以便采取相应的措施;
2、保证桩架摆放准确,使锤心正对槽段中心线;加固桩架,减少冲锤过程中桩架的晃动;
3、冲锤的直径控制在80-82CM之内,经常检查锤牙的磨损程度,及时修补或更换;
4、冲孔过程中,提锤的高度控制2.5M之内,冲锤撞击岩面时,保证钢丝绳仍受拉力,以保持冲锤的竖直;
5、及时换浆,保持一定的泥浆浓度,防止粘锤;
6、冲孔至岩土分解面时,低锤密击,直至进入岩层内部;
7、加强观察,发现偏孔及时采取措施予以纠正。
Stone Pile class quality of technical disclosure to prevent the partial hole content:
According to the reasons causing partial hole in the construction process to take the following preventive measures:
1, according to the geological information provided by Party A and the adjacent slot of the geological conditions, in a timely manner to know the depth into the rock, mezzanine as well as the slope of rock surface in order to take appropriate measures;
2 post rack placed to ensure accurate to hammer heart is the center line of the trough section; reinforcement pile frame, reduce the hammer during the rock pile holder;
3, hammer of the diameter of control within the 80-82CM, regular checks of hammer teeth wear, timely repair or replacement;
4, punching process, provide a high degree of control 2.5M hammer within the hammer hit rock face, the guarantee still pull rope to keep the hammer in the vertical;
5, in time for slurry, the slurry to maintain a certain concentration, to prevent sticking hammer;
6, punching to the decomposition of surface rock, the low-density blow hammer until the rock into the interior;
7, to enhance observation, found that partial hole to take timely measures to correct.
帮助 收藏 报错 评论>> |
本类栏目导航
总点击排行
- 天正建筑2013最新64位破解版
- 160514次
- Autocad2013 64位32位破解版附带注册机
- 148307次
- 天正建筑8.5破解版
- 144041次
- autocad2012 64位32位 破解版(附注册
- 137474次
- 天正建筑8.2破解版
- 123392次
- autocad2010免费下载(简体中文版)
- 97140次
- CAD2008注册机及使用说明
- 80806次
- 免费农村房屋设计图
- 73715次
- cad图集大全
- 56756次
- 11g101图集全套下载
- 45286次
- 路缘石安装技术交底记录
- 1374次
- 施工组织设计交底记录
- 1155次
- 公路施工安全技术交底
- 1047次
- 检查井施工技术交底
- 868次
- 土石方开挖施工技术交底记录
- 829次
- 排水工程雨水管施工技术交底
- 757次
- 边沟盖板安装施工技术交底记录
- 756次
- 雨水管道安装技术交底记录
- 719次
- 墩柱施工技术交底
- 668次
- 综合管沟沟槽开挖、回填施工技术交底
- 609次