一、准备工作
1、回填前预制管节现场铺设管的现浇混凝土基础强度、接口抹带或预制构件现场装
配的接缝水泥砂浆强度不小于5N/mm2。现场浇筑混凝土的强度达到设计规定。
2、回填前将槽底杂物(砖石、木块草包、模板及支撑设备等)清理干净,保证沟槽内
没有积水。
3、经监理工程师验管合格后进行。
二、回填材料
回填材料采用经试验检验合格的灰土、砂、砂砾。要求砂石级配良好,不含植物残体、
垃圾等杂物。砾石粒径约在0.5mm~30mm 之间,灰土配比按监理指示执行。
三、回填方法
1、回填顺序:还土时按基底排水方向由高至低分层进行,同时管腔两侧应同时进行。
2、填土要求:槽底至管顶以上0.5m 范围内及在抹带接口处、防腐绝缘层或电缆周围,
采用砂砾石回填;保证回填土的含水量,按土类和采用的压实工具控制在最佳含水量附近;
需要拌和的回填材料,应在运入槽内前拌和均匀,不得在槽内拌和。
3、填土方法:管道两侧沟槽底至管顶以上50cm 的范围内还土,由沟槽两侧对称进
行采用人工还土,不得直接扔在管道上;超过管顶50cm 以上时再采用机械还土。还土时
采用分层铺设夯实,层厚25cm,采用人工摊平。
4、夯实方法:管道两侧沟槽底至管顶以上50cm 的范围内采用人工夯实,超过管顶
50cm 以上采用蛙式打夯机夯实,砂、砂砾回填分层灌水、用插入式振动器振动,以达到设
计的压实度要求。回填压实逐层进行,且不得损伤管道。管道两侧和管顶以上50cm 范围
内的压实,采用薄铺轻夯夯实,管道两First, preparatory work
1, filling the scene before the prefabricated pipe sections cast concrete foundation laying pipe strength, interface wipe with or prefabricated on-site installation
Strength of the joints with cement mortar not less than 5N/mm2. On-site pouring of concrete strength of the design requirements.
2, bottom of the tank before filling debris (brick, wood idiot, templates, and support equipment, etc.) to clean up, to ensure groove
No water.
3, test tube by the supervising engineer qualified for.
Second, backfill material
Backfill material is qualified by the pilot test dust, sand, gravel. Well graded sand and gravel required, without plant debris,
Garbage and other debris. Gravel size between about 0.5mm ~ 30mm, dust ratio of supervision by the instructions.
3, backfill method
1, filling the order: also soil, according to the direction of high to low basal drainage layer to conduct, while the lumen on both sides should be at the same time.
2, filling requirements: 0.5m above bottom to the top tube and in the context of wiping with interfaces, anti-corrosion insulation or cable around
Backfill with gravel; ensure backfill moisture content, according to the compaction of soil type and use the best tools to control water content in the vicinity;
Require mixing of the backfill material should be evenly into the tank before the mixing, not mixing in the tank.
3, filling method: pipeline trench bottom to the sides above the top tube is also within 50cm of soil from trench into the side symmetry
Rows of artificial soil also may not be directly thrown into the pipe; more than 50cm above the top tube and then also by mechanical soil. Also soil,
Stratified roll compaction, thickness 25cm, artificial shared flat.
4, compaction method: pipeline trench on both sides of 50cm above the bottom to the top management within the framework of artificial compaction, over the top tube
More than 50cm frog tampers with compacted sand, gravel backfill layer irrigation, using plug-in vibrator vibration, to achieve the set
Total degree of compaction requirements. Backfill compaction step by step, and may not damage pipes. Pipe and tube top over 50cm on both sides of the scope of
The compaction, tamping rammer with thin light shop, pipe 2