一、施工准备
1、明挖管道铺设接口强度达到设计强度80%;
2、选定好砂、石子、水泥、砖、钢筋等原材料,送样到试验室作原材料试验,依据图
纸要求进行试配,现场按照试验室提供的配合比根据现场砂石含水量确定施工配合比。
二、施工方法
(一)、检查井砌筑
1、井底基础与管道基础同时浇筑。
2、流槽一定与检查井壁同时砌筑。表面用砂浆分层压实抹光,流槽与上下游管道接顺,
管内底高程符合混凝土管道基础及安装的允许偏差。
3、砌筑井室,用水冲净基础后,先铺一层砂浆,再压砖砌筑,做到满铺满挤,砖与砖
间灰缝保持1cm。
4、与检查井连接的所有管道端头,要经过凿毛处理并要清理干净,保证管道与检查井
井壁结合牢固。
5、砂浆拌和均匀,保证砌筑砖含水量为10~15%,砌体不得有竖向通缝,必须为上、
下错缝,内外搭接。如井身不能一次砌完,在二次接高时,将原砖面上的泥土杂物清理干净,
然后用水清洗砖面并浸透。
6、砖砌圆形检查井时,随时检测直径尺寸,当需要收口时,如为四面收进,则每次收
进不大于30mm;如为三面收进,则每次收进不大于50mm。砌筑检查井的内壁应用原浆勾
缝,有抹面要求时,内壁抹面应分层压实,外壁用砂浆搓缝并严实。
7、检查井接入圆管的管口应与井内壁平齐,当接入管径大于300mm 时,砌砖圈加固。
管子穿越井室壁或井底,留有30~50mm 的环缝,用油麻-水泥砂浆,油麻-石棉水泥或粘土
填塞并捣实。
8、砌筑井内踏步时,随砌随安,位置正确。踏步安装后,在砌筑砂浆或混凝土未达到
规定抗压强度前不得踩踏。混凝土井壁的踏步在预制或现浇时安装。First, construction preparation
1, cut and cover pipeline Interface strength to meet the design strength of 80%;
2, good selection of sand, gravel, cement, bricks, steel and other raw materials, send samples to laboratories for testing raw materials, according to Figure
Test paper with the requirements, on-site laboratory provided in accordance with the ratio of water content determined according to the construction site sand and gravel mix.
Second, construction method
(A), check the well masonry
1, bottom pouring the same time base and pipeline infrastructure.
2, groove and inspection of certain masonry wall at the same time. Surface layer compaction trowel with mortar, tank and flow along the upstream and downstream channel access,
Pipe invert base line and installed concrete pipe tolerances.
3, masonry well chamber, the foundation of water rinse, Xian Pu layer of mortar, and then press brick building, so that at least covered with crowded, brick and tile
Between the mortar joint to maintain 1cm.
4, well connected with the inspection of all pipeline ends, to go through a hammer handle and to clean up the hair to ensure that pipeline and inspection wells
Combined with a solid wall.
5, uniform mixing mortar, brick masonry to ensure the moisture content of 10 ~ 15%, not a vertical straight joint masonry, must, on
The wrong slot, inside and outside the overlap. Such as the casing can not complete a puzzle, the second pick in the high, the original brick surface of the earth to clean up debris,
Then use water to clean the tile surface and soak.
6, circular brick inspection wells, the diameter of any test, shut up when needed, such as when incorporated into the four sides, then each received
Into not more than 30mm; the case of income into the three sides, is incorporated into each no larger than 50mm. Well masonry wall applications Check puree hook
Joint, there finishing requirements, wall finishing should be layered compaction, the outer wall with mortar joints and the tightly rubbing.
7, check the nozzle tube wells access should be flush with the wall Well, when access is greater than 300mm diameter, the brick ring reinforcement.
Tube through the well wall or bottom, left 30 ~ 50mm in girth, hemp oil - cement mortar, Yau Ma Tei - asbestos cement or clay
Filling and tamping.
8, when no progress masonry wells, with the puzzle with the security, the correct position. Stepping installed in mortar or concrete has not reached
Compressive strength requirement shall not be trampled before. Precast concrete wall of stepping in when the installation or place.