垃圾池设置技术交底书.doc
交底内容:
根据《建设工程项目管理规范》关于“建筑垃圾、渣土应在指定地点堆放和在施工现场设置机动车车辆冲洗设施”的规定,特要求各路基施工队、浆砌防护队伍、桥涵施工队在施工现场及施工队驻地设置垃圾池,并按规范要求在指定地方堆放弃渣,具体要求有:
1、 要求每个施工场所以及施工队驻地均设置相应的垃圾池。
2、 垃圾池要求人工开挖,四周坑壁的坡比采用1:0.3。
3、 垃圾池的大小应满足各施工场所以及施工队驻地的的垃圾临时存放需要。
4、 要求施工队在垃圾池的选址上尽量避免行人出入处,并设好防护,原则上不允许在路基填筑范围设置垃圾池。
Cards on the table contents:
According to "Construction Project Management Standards" on "construction debris, dirt should be piled in designated areas and at the construction site to set motor vehicle washing facilities" requirement, requiring special roadbed construction team, mortar and protection force, bridge construction team construction site and construction team to set La Jichi resident, in accordance with specifications Spoil piling up in designated areas, specific requirements are:
1, requires each resident construction sites and construction team have set the corresponding La Jichi.
2, La Jichi required manual excavation, around the Pit of the slope ratio with 1:0.3.
3, La Jichi size should meet the needs of the resident construction sites and construction team of the waste for temporary storage needs.
4, requested the location of the construction team in La Jichi avoid pedestrian access on the Department and set better protection, in principle, allow the scope to set La Jichi subgrade construction.
帮助 收藏 报错 评论>> |
本类栏目导航
总点击排行
- 天正建筑2013最新64位破解版
- 160514次
- Autocad2013 64位32位破解版附带注册机
- 148307次
- 天正建筑8.5破解版
- 144042次
- autocad2012 64位32位 破解版(附注册
- 137474次
- 天正建筑8.2破解版
- 123392次
- autocad2010免费下载(简体中文版)
- 97140次
- CAD2008注册机及使用说明
- 80806次
- 免费农村房屋设计图
- 73715次
- cad图集大全
- 56756次
- 11g101图集全套下载
- 45286次
- 路缘石安装技术交底记录
- 1374次
- 施工组织设计交底记录
- 1155次
- 公路施工安全技术交底
- 1047次
- 检查井施工技术交底
- 868次
- 土石方开挖施工技术交底记录
- 829次
- 排水工程雨水管施工技术交底
- 757次
- 边沟盖板安装施工技术交底记录
- 756次
- 雨水管道安装技术交底记录
- 719次
- 墩柱施工技术交底
- 668次
- 综合管沟沟槽开挖、回填施工技术交底
- 609次