连续墙、冲桩各工种质量技术交底卡.doc
冲桩班技术交底内容:
1.桩架上的机长和成员应持证上岗。
2.桩架人员每天交班都要交底,将上一个台班冲孔记录交代清楚。
3.在成孔过程中,如发现偏孔应及时采取纠偏措施。当进岩时,应做好取样、分类、记录等工作。
4.钢筋笼入槽前,必须对槽底泥浆和沉淀物进行置换和清除。置换量不小于该槽段总体积的1/3置换和清除必须采用底部抽吸,顶部补浆方法。使底部泥浆比不大于1.3。沉淀淤积物(沉渣)厚度不得超过规范要求。
5.钢筋笼的构造应有利于入槽后的准确就位和固定。吊运过程中、不应产生不可恢复的变形,不得强行入槽。钢筋笼应在泥浆置换合格后及时入槽后至浇筑砼时的总停置时间不宜超过6小时。浇筑砼时应防止钢筋笼上浮。
6.砼应采用导管法浇筑,导管按需要长度拼接。导管距槽段端部不宜大于2m;砼的浇筑速度不宜小于每小时上升3~4m,导管插入砼
Stone Pile class technical disclosure content:
1. Browse the captain and the members of the pile should certificates.
2. Pile frame shift each day and have correspondent, will be on a station class punching record clearly.
3. In the hole process, if found to be partial hole to take timely corrective measures. When into the rock, they should do a good job sampling, classifying, recording and so on.
4. Reinforcement cage into the tank prior to the mud and sediment on the bottom for replacement and cleaning. Replacement is not less than the slot, and the total volume of 1 / 3 of replacement and removal must be the bottom of the pump, fill the top of slurry method. To the bottom of the slurry is not greater than 1.3 than. Precipitation sludge (sediment) may not exceed the thickness specifications.
5. Reinforcement cage of the structure should be conducive to the exact place into the trough and fixed. Lifting process, should not result in irreversible deformation, not forced into the slot. Reinforcement cage shall be replaced in the mud into the tank after passing the post in time to pouring concrete when the total holding time should not exceed 6 hours. Pouring concrete should be reinforced to prevent the floating cage.
6. Concrete should be poured catheter, catheter length required stitching. Catheter tip from the slot section of not greater than 2m; the pouring of concrete not less than the hourly rate rose 3 ~ 4m, catheterization concrete
帮助 收藏 报错 评论>> |
本类栏目导航
总点击排行
- 天正建筑2013最新64位破解版
- 160514次
- Autocad2013 64位32位破解版附带注册机
- 148307次
- 天正建筑8.5破解版
- 144042次
- autocad2012 64位32位 破解版(附注册
- 137474次
- 天正建筑8.2破解版
- 123392次
- autocad2010免费下载(简体中文版)
- 97140次
- CAD2008注册机及使用说明
- 80806次
- 免费农村房屋设计图
- 73715次
- cad图集大全
- 56756次
- 11g101图集全套下载
- 45286次
- 路缘石安装技术交底记录
- 1374次
- 施工组织设计交底记录
- 1155次
- 公路施工安全技术交底
- 1047次
- 检查井施工技术交底
- 868次
- 土石方开挖施工技术交底记录
- 829次
- 排水工程雨水管施工技术交底
- 757次
- 边沟盖板安装施工技术交底记录
- 756次
- 雨水管道安装技术交底记录
- 719次
- 墩柱施工技术交底
- 668次
- 综合管沟沟槽开挖、回填施工技术交底
- 609次