水泥稳定碎石层施工技术交底记录.doc
交底内容:
1、 待下层4%水泥石屑稳定层经验收合格后,在其上铺筑35cm6%水泥稳定级配碎石层。
2、 水泥碎石稳定层应用12吨以上的压路机碾压。
3、 必须饱湿养生,不使稳定碎石基层表面干燥,也不应忽干忽燥。
4、 用于水泥碎石基层的碎石,其压碎值不大于30%,硫酸盐含量不超过0.25%,有机质含量不大于2%。最大粒径不超过37.5mm(方孔筛)。
5、 集料拌和时的含水量比最佳含水量大0.5%~1.0%,以补偿施工过程中水份的蒸发;并保证和后的含水量稍高于最佳含水量,以弥补碾压过程中水分的损耗。
6、拌和好的混合料尽快摊铺,做到自第一次拌和机内加水至完成压实工作的时间不超过3小时,并不小于终凝时间。
7、不同施工段的衔接处,采用搭接处理,前一段拌和整形后,留5~8m不进行碾压,后一段施工时,前段留下未压的部分再加适量水泥重新拌和,并与后一段一起碾压。
Cards on the table contents:
1, to be 4% lower stable layer of cement stone chips after their acceptance, in its last paving 35cm6% cement stabilized gravel layer.
2 Application stable layer of cement 12 tons of gravel over the roller compacted.
3, must be full wet curing, do not make stabilized gravel surface dry and should not suddenly dry suddenly dry.
4, cement gravel gravel, crushed its value is not greater than 30%, sulfate content of no more than 0.25%, organic matter content of not more than 2%. Maximum diameter of no more than 37.5mm (square hole sieve).
5, when the water content of aggregate mixing water content than the best large 0.5% to 1.0%, to compensate for evaporation of water during construction; and guarantee and after the water content slightly higher than the optimum water content, to make up for rolling process of water loss.
6, mixing a good mix paving as soon as possible, so that the first time since the mixing machine with water to complete the compaction work time is not more than three hours, not less than the final setting time.
7, the interface between different construction office segment, using lap treatment, before a plastic mixing, the remaining 5 ~ 8m without RCC, after a period of construction, leaving no pressure part of the preceding plus appropriate cement re-mixing, and with with time after rolling.
帮助 收藏 报错 评论>> |
本类栏目导航
总点击排行
- 天正建筑2013最新64位破解版
- 160514次
- Autocad2013 64位32位破解版附带注册机
- 148307次
- 天正建筑8.5破解版
- 144042次
- autocad2012 64位32位 破解版(附注册
- 137474次
- 天正建筑8.2破解版
- 123392次
- autocad2010免费下载(简体中文版)
- 97140次
- CAD2008注册机及使用说明
- 80806次
- 免费农村房屋设计图
- 73715次
- cad图集大全
- 56756次
- 11g101图集全套下载
- 45286次
- 路缘石安装技术交底记录
- 1374次
- 施工组织设计交底记录
- 1155次
- 公路施工安全技术交底
- 1047次
- 检查井施工技术交底
- 868次
- 土石方开挖施工技术交底记录
- 829次
- 排水工程雨水管施工技术交底
- 757次
- 边沟盖板安装施工技术交底记录
- 756次
- 雨水管道安装技术交底记录
- 719次
- 墩柱施工技术交底
- 668次
- 综合管沟沟槽开挖、回填施工技术交底
- 609次