水泥稳定碎石底基层、基层技术交底记录.doc
交底内容:
1、路槽验收
路槽整理成形后,对压实度、高程、平整度、宽度、横坡度等要经监理工程师验收合格后方可进行下步工序施工。
2、施工放样
采用拓普康全站仪放出控制点,用经纬仪加密,每隔10米打出中心桩和边桩,在设定桩位处钉设钢钎,测定高程,挂好施工线。
3、水泥碎石拌和
混合料的拌和采用集中拌和,在正式拌和前,先调试所用的厂拌设备,从表盘、水箱、水泥灌、各下料仓、皮带输送机、空压机、出料仓到各部位线路均调到最佳状态,然后按试验配合比进行试拌,确定施工配合比。
4、运输和摊铺
(1)、运输:混合料的运输一律采用箱板密封良好的10T以上的自卸汽车,其车箱底始终保持洁净。
(2)、摊铺:
5、碾压遍数:先用振动压路机稳压2遍,再振压4遍,再静压2遍。
6、养生
水泥碎石碾压完成后,立即覆盖草席洒水养护。养生期
Cards on the table contents:
1, Road tank inspection
Road tank after finishing forming, on the degree of compaction, elevation, roughness, width, cross slope, etc. to acceptance by the Supervising Engineer after the construction process before the next step.
2, construction setting
Released by Topcon total station control points, using theodolite encryption, every 10 meters play center and edge pile pile pile is located in the set screw located drill rod, measured height, hang up the construction lines.
3, mixing cement gravel
Mixture mixing centralized mixing, mixing in the official before commissioning the plant mixing equipment used, from the dial, water tanks, cement filling, the lower hopper, belt conveyor, air compressor, a hopper to different parts of lines are transferred to the best condition, and then press the test with the test-mix ratio to determine the construction mix.
4, transport and spreading
(1), transport: transport of mixture shall be sealed with box board for more than a good 10T dump truck, always maintain the cleanliness of their vehicles Bottom.
(2), paving:
5, rolled several times: first with a vibratory roller regulator 2 times 4 times and then vibration pressure, static pressure and then 2 times.
6, health
Rolling Stone after the completion of cement, straw mats covered immediately sprinkler maintenance. Health of
帮助 收藏 报错 评论>> |
本类栏目导航
总点击排行
- 天正建筑2013最新64位破解版
- 160514次
- Autocad2013 64位32位破解版附带注册机
- 148307次
- 天正建筑8.5破解版
- 144042次
- autocad2012 64位32位 破解版(附注册
- 137474次
- 天正建筑8.2破解版
- 123392次
- autocad2010免费下载(简体中文版)
- 97140次
- CAD2008注册机及使用说明
- 80806次
- 免费农村房屋设计图
- 73715次
- cad图集大全
- 56756次
- 11g101图集全套下载
- 45286次
- 路缘石安装技术交底记录
- 1374次
- 施工组织设计交底记录
- 1155次
- 公路施工安全技术交底
- 1047次
- 检查井施工技术交底
- 868次
- 土石方开挖施工技术交底记录
- 829次
- 排水工程雨水管施工技术交底
- 757次
- 边沟盖板安装施工技术交底记录
- 756次
- 雨水管道安装技术交底记录
- 719次
- 墩柱施工技术交底
- 668次
- 综合管沟沟槽开挖、回填施工技术交底
- 609次