预制混凝土板块和水泥方砖路面铺设施工技术交底.doc
交底内容:
预制混凝土板块和水泥方砖路面铺设施工
1 范围
本工艺标准适用于工业与民用建筑的厂区、庭院道路及停车场等,铺设预制混凝土板块和水泥方格砖面层。
2 施工准备
2.1 材料及主要机具:
2.1.1 预制混凝土板块:强度不应小于20MPa,规格为49.5cm×49.5cm,路面块材厚度为10cm以上,人行道及庭院块材厚度为5cm以上。进场时应有出厂合格证、混凝土强度试压记录。并对混凝土板块进行外观检查,表面要求密实,无麻面、裂纹和脱皮,边角方正,无扭曲、缺角、掉边。板块允许偏差:长、宽±2.5mm.,厚度±2.5mm,长度≥400mm平整度为lmm,长度≥800mm,平整度为2mm。
2.1.2 水泥方格砖:尺寸为25cm×25cm×5cm,抗压、抗折强度符合设计要求,其规格、品种按设计要求选配,外观边角整齐方正,表面光滑、平整,无扭曲、缺角、掉边现象,进场时应有出厂合格证。
2.1.3 砂:粗砂、中砂。
2.1.4 水泥:325号以上普通硅酸盐水泥或矿渣硅酸盐水泥,有出厂合格证。
2.1.5 磨细生石灰粉:提前48h熟化后再用。
2.1.6 预制混凝土与路牙子,按图纸尺寸及强度等级提前预制加工。
2.1.7 主要机具:小水桶、半截桶、扫帚、平铁锹、铁抹子、大木杠、小木杠、筛子、窗纱筛子、喷壶、锤子、橡皮锤、錾子、溜子、板块夹具、扁担、手推车等。
2.2 作业条件:
2.2.1 庭院或小区的地下各种管道,如污水、雨水、电缆、煤气等均施工完,并经检查验收。
2.2.2 庭院或小区的场地已进行基本平整,障碍物已清除出场。
2.2.3 庭院或小区道路已放线且已抄平,标高、尺寸已按设计要求确定好。路基基土已碾压密实,密实度符合设计要求,并已经进行质量检查验收。
3 操作工艺
Cards on the table contents:
Precast concrete blocks and cement cubes laying construction
1 Scope
This technology is applicable to industrial and civil construction plant, roads and parking lot garden, laying pre-cast concrete blocks and cement tile surface layer of the box.
2 construction preparation
2.1 Materials and main equipment:
2.1.1 Precast Concrete blocks: strength of not less than 20MPa, specifications for the 49.5cm × 49.5cm, 10cm road block material thickness above the sidewalk and the courtyard bulk thickness of more than 5cm. Approach should have factory certification, pressure test records of concrete strength. And the appearance of concrete blocks to check dense surface required, no anesthesia face, cracks and peeling, edges Founder, no distortion, chipping, out side. Plate tolerance: length, width ± 2.5mm., Thickness ± 2.5mm, length ≥ 400mm flatness is lmm, length ≥ 800mm, flatness is 2mm.
2.1.2 Cement brick box: size of 25cm × 25cm × 5cm, compressive and flexural strength design requirements, specifications, design requirements according to variety selection, Founder and tidy appearance of the corners, smooth surface, no distortion, missing corner, out side of the phenomenon, there should be entering the factory certification.
2.1.3 Sand: coarse sand, medium sand.
2.1.4 Cement: ordinary portland cement 325 or more or slag cement, with a factory certificate.
2.1.5 Ground quicklime powder: 48h ahead of time and then with maturation.
2.1.6 Precast Concrete and Road teeth child, by drawing size and strength grade ahead of pre-processing.
2.1.7 Main equipment: a small bucket, half barrels, brooms, flat shovels, iron trowel, large mugang, small mugang, sieve, sieve screens, watering can, hammer, rubber hammer, chisel, the valve plate fixture, pole, trolleys.
2.2 Operating conditions:
2.2.1 garden or plot of ground the various channels, such as sewage, water, cable, gas Deng Jun construction completed, and after inspection and acceptance.
2.2.2 garden or plot of the site has a basic level, obstacles have been cleared appearance.
2.2.3 courtyard or residential roads in actinomycetes and has been copied level, elevation, size, design requirements have been determined according to good. Compaction of subgrade soil has been compacted, compaction meets the design requirements and has the quality inspection and acceptance.
3 Operation Process
帮助 收藏 报错 评论>> |
本类栏目导航
总点击排行
- 天正建筑2013最新64位破解版
- 160514次
- Autocad2013 64位32位破解版附带注册机
- 148307次
- 天正建筑8.5破解版
- 144042次
- autocad2012 64位32位 破解版(附注册
- 137474次
- 天正建筑8.2破解版
- 123392次
- autocad2010免费下载(简体中文版)
- 97140次
- CAD2008注册机及使用说明
- 80806次
- 免费农村房屋设计图
- 73715次
- cad图集大全
- 56756次
- 11g101图集全套下载
- 45286次
- 路缘石安装技术交底记录
- 1374次
- 施工组织设计交底记录
- 1155次
- 公路施工安全技术交底
- 1047次
- 检查井施工技术交底
- 868次
- 土石方开挖施工技术交底记录
- 829次
- 排水工程雨水管施工技术交底
- 757次
- 边沟盖板安装施工技术交底记录
- 756次
- 雨水管道安装技术交底记录
- 719次
- 墩柱施工技术交底
- 668次
- 综合管沟沟槽开挖、回填施工技术交底
- 609次