施工准备计划

我单位在漯平高速公路No.5合同段开工前的施工准备工作已拟定了详细计划,现呈交给贵办,请贵办审核并给予指导。
详细施工准备计划安排如下:
一、临时房屋建设
我单位已于2003年8月18日开始进行临时房屋建设。由于施工现场附近没有例行的住房可以租用,我单位研究决定将五标段项目经理部设在舞阳县九街乡王桥街东侧,黄石公路与拟建高速公路之间,占地2亩,房屋全部采用活动板房,计划在8月25日入住,并做好排污、排水设施。
二、试验室组建及试验工作安排
试验室修建在项目经理部内,地板用素砼硬化,试验室内部装修。包括标养室,试验室面积65平方米,采用活动板房搭建,计划9月10日修建完毕。试验仪器、设备计划在9月20日配套安装完毕。
在我单位试验室认证前,土样试验计划委托漯河市公路局质检站做填料取样工作,根据九街乡协调办安排情况,进行取样。待填料试验
Construction preparedness plans

I units in the Luo section of Highway No.5 started before the construction contract has been developed to prepare detailed plans are submitted to your office, please do your review and guidance.
Prepare detailed construction plans as follows:
1, temporary housing
My unit was on Aug. 18, 2003 to begin construction of temporary housing. As the construction site near the house can be rented there is no routine, I decided to five units of the Department of Lot Project Manager based in the east of Wuyang 9 parastic Wang Kiu, between Yellowstone Highway and the proposed highway, covering 2 acres Housing used in all portables, plans to stay on August 25, and make the sewage and drainage facilities.
Second, the laboratory set up and test work
Laboratory within the Ministry to build the project manager, floor hardening using plain concrete, laboratory internal decoration. Including the standard curing room, the laboratory area of 65 square meters, with activity board room set up, plan on Sept. 10 was completed. Test apparatus, equipment plans on Sept. 20 supporting installed.
Certified laboratory in our unit before the trial soil samples Luohe City Highway Bureau commissioned to do quality inspection stations fill sampling, according to the arrangement in nine parastic Coordination Office to conduct sampling. When filling test
 