冲击钻机施工桩基

1.施工方法
    采用GCF型正循环钻机冲击成孔,钻头采用“十字型”,泥浆护壁,泥浆比重1.4~1.8,含砂率6%,胶体率大于95%。孔口护筒采用钢护筒,护筒壁厚6mm以上,旱地及河滩采用挖埋方式埋置,浅水区采用筑岛围堰施工,深水区设栈桥及工作平台。钻进冲程根据地层情况控制:一般地层2~3m,开孔时及溶洞钻进时0.8~1.5m。终孔后采用换浆法清孔。钢筋笼采用分节预制,节长8~10m,吊装焊接入孔。桩身砼采用φ30垂直导管,拔塞法灌注水下砼。
    溶洞地层桩基施工:上覆层扩大孔径0.2m钻孔至基岩面下0.5m处,下入略大于原设计桩径0.1m的钢护筒至孔底以稳定上覆层。钢护筒采用1cm以上厚度的钢板分节卷制,节长2~4m,吊装入孔焊接。填充溶洞处理:投入片石及粘土,小冲程冲砸挤石造壁加固孔壁;未填充溶洞处理:投入袋装片石及粘土或水泥筑成岛状,然后小冲程钻孔通过。
2.施工工艺流程
2.1一般桩基施工工艺流程(见图1)
2.2溶洞桩基施工工艺流程(见图2)
3.劳动力组织及进度指标
3.1劳动力组织
钻机工班:采用三班八小时工作制;每班设班长1名,值班电工1名,汽车吊车司机2名,钻机司机2名/台,电焊工1名/台,勤杂工1名/台。灌砼工班:采用三班八小时工作制,每班设班长1名,值班电工1
Percussion Drill Pile Construction

1. Construction Method
    
GCF-based cycle drill by now the impact of drilling, drill a "Cross", Slurry Wall, mud weight of 1.4 to 1.8, the rate of 6% sand, gel> 95%. Orifice casing with steel casing, casing thickness 6mm or more, dry and flood embedded with the trenching method, shallow water with the island cofferdam construction, Sham Shui Po District, located bridge and working platform. Stratigraphic drilling stroke cases under control: the general stratigraphic 2 ~ 3m, and the cave when drilling holes when the 0.8 ~ 1.5m. After the final hole for pulp used to clean hole. Use of prefabricated reinforcement cage section, long section of 8 ~ 10m, hoisting welded into the hole. Concrete pile with φ30 vertical conduit, pull plug method pouring underwater concrete.
    
Pile Foundation Construction cave formation: the overlying layer to expand drilling to the bedrock surface diameter 0.2m 0.5m under the Department, under the original design into the pile diameter slightly larger than 0.1m of steel casing to the bottom of hole to stabilize the coating. The casing is more than 1cm thick section steel plate rolling, section length 2 ~ 4m, lifting into the hole soldering. Filled cave processing: input and stones and clay, smashing a small stroke red stone wall extrusion reinforced hole wall; not filled cave treatment: put bags and stones and clay or cement built into the island, and then drilling through the small stroke.
2. Construction Process
2.1 General Pile Foundation Construction Process (see Figure 1)
2.2 Pile Foundation Construction process caves (see Figure 2)
3. Labor organizations, and progress indicators
3.1 Labor Organization
Drilling Engineering Class: The Three eight-hour day; class monitor a set, an electrician on duty, vehicle crane driver 2, drill driver 2 / platform, welders 1 / Taiwan, porters 1 / Taiwan . Concrete Engineering Course Irrigation: The Three eight-hour day, the class set up a squad leader on duty electrician 1