山东省安装工程消耗量定额解释.rar
山东省安装工程消耗量定额解释
第一册机械设备安装工程
1.定额中未包括大型设备吊装所用的施工机械费用,请问什么样的设备为大型设备?其所需的施工机械费用如何计算?
答:大型设备是指整体设备重量大于60吨的设备。本册定额中未考虑大型设备的吊装机具,发生时应按施工方案另行计算。
2.本册中设备单机试运转包括的内容是哪些?
答:设备单机试运转属于整体设备安装内容范畴。其工作内容应按相应"规范"中规定的为准;不包括机械设备部分以外各系统(如电气、仪表、通风等系统)的试验、调整、试运转。单机试运转所用的除水、电、气、油、燃料需另计以外的其他材料、人工及机械均已包括在设备安装定额内。
3.本册定额中是否包括设备单机试运转时的配合电工?
答:机械设备安装定额内,已包括试运转中所必须配合的电工。机械设备的电气部分的安装、调整、试验、试运转所需的电工,则包括在相应电气安装定额内。
4.设备本体范围内的管道及附件没有随设备配套供应,需现场进行配制后安装,应怎样计算该部分的制作安装费?
Shandong Province to explain the installation of fixed consumption
Volume installation of machinery and equipment
1. Fixed equipment not included in large-scale construction machinery used for hoisting the cost, I ask what kind of equipment for large equipment? The construction equipment required for the calculation of the cost?
A: The large-scale equipment is the equipment in the weight of more than 60 tons of equipment. This book is not considered large scale lifting equipment machinery, construction time of the program should be counted.
2. The volume of equipment, including the contents of the single test run what?
A: The equipment belongs to the whole installation commissioning single content area. The content of their work should be corresponding "standard" in the subject under; does not include machinery and equipment other than parts of systems (such as electrical, instrumentation, ventilation system) testing, adjustment, commissioning. Used stand-alone addition to commissioning of water, electricity, gas, oil, fuel, pay extra than other materials, labor and machinery are included in the fixed installation inside.
3. Fixed in this book are included with the device when the stand-alone commissioning electrician?
A: The installation of fixed machinery and equipment, which has been included in the commissioning electrician must meet. Electrical parts of machinery and equipment installation, adjustment, testing, commissioning the necessary electrical, are included within the corresponding fixed electrical installation.
4. Body within the pipeline equipment and accessories not matching supply with the equipment, be installed after site preparation, how to calculate the part of the production installation fee?