泌桐高速箱梁模板计算及施工资料.doc
箱梁模板计算及施工资料
现浇预应力钢筋混凝土箱梁施工
单箱截面,截面尺寸为梁高1.5米、梁顶宽8.96米,具体尺寸形式见图10-1。箱梁截面尺寸:
图10-1 箱梁截面尺寸详图
10.1 施工顺序
预应力混凝土箱梁采用满布支架现场浇筑混凝土的施工方法。箱梁混凝土浇筑采用二次浇筑:第一次浇筑底板和腹板,第二次浇筑顶板。预应力施工采用后张法预应力施工工艺。具体工艺流程见图10-2。
10.2 现浇砼施工
10.2.1 支架体系
预应力钢筋混凝土连续箱梁支架采用满堂红式支架体系。
Box girder calculation and construction materials
Prestressed concrete box girder
Single box section, the section size is 1.5 meters high beam, beam top width of 8.96 m, the specific size of the form shown in Figure 10-1. Box section size:
Figure 10-1 box section size Detailing
10.1 The construction order
Prestressed concrete box beam scaffolding-situ concrete construction method. Box pouring concrete placement by the second: the first floor, and web casting, the second pouring roof. Construction using prestressed post-tensioned construction technology. Specific process shown in Figure 10-2.
10.2 situ concrete construction
10.2.1 Support System
Prestressed concrete continuous Box Beam stent system with full house.
帮助中心 收藏 >>> |
本类栏目导航
总点击排行
- 天正建筑2013最新64位破解版
- 173549次
- Autocad2013 64位32位破解版附带注册机
- 154872次
- 天正建筑8.5破解版
- 146385次
- autocad2012 64位32位 破解版(附注册
- 139021次
- 天正建筑8.2破解版
- 127265次
- autocad2010免费下载(简体中文版)
- 98144次
- 免费农村房屋设计图
- 90905次
- CAD2008注册机及使用说明
- 84340次
- 11g101图集全套下载
- 78882次
- cad图集大全
- 67445次
- 项目开工仪式上的讲话稿
- 7911次
- 总工程师岗位职责
- 5616次
- 项目部管理制度汇编
- 2290次
- 钢筋班组劳务分包合同
- 2066次
- 低值易耗品管理制度
- 1498次
- 工程部管理制度
- 1492次
- 钢筋工承包合同
- 1233次
- 财务印章管理制度
- 1071次
- 公司安全专项施工方案专家论证审查制度
- 964次
- 晴雨表
- 962次