黄埔大桥二标段工程质量计划.doc
工程质量计划
标段全长693.607 m。分为地面道路、排水与高架桥三部分。高架桥为独柱或双柱单幅桥,
桥长为693.607m;地面道路为道路改造工程,即梅东路~空军医院区段拓宽至50m,沙
河涌桥亦相应扩宽;排水工程包括雨水管和污水管。
一、质量方针
精心施工、高效优质,拓宽技术、保持优势,竭诚服务、顾客满意
二、质量计划范围
本质量计划仅适用于内环路放射线黄埔大道二标段工程。
三、工程项目质量目标
推行全面质量管理,工程一次成优,创优良样板工程。工程质量达到:
1、分项工程合格率100%,优良率95%;
2、单位工程竣工质量优良;
3、创无质量通病工程,杜绝重大质量事故。
四、质量控制原则
1、坚持“百年大计,质量第一”的原则。
2、以人为本,把人作为控制的动力,调动人的积极性、创造性,增强空的责任感,树
立“质量第一”观念,提高人的素质,避免人的失误,以人的工作质量保证工序质量和
工程质量。
3、预防为主:把对质量的事后检查,转为对质量的事前控制,把对工程产品质量的检
查,转为对工作质量的检查,对工程产品质量的检查和对中间Project Quality Plan
Tenders full 693.607 m. Into the road surface, drainage and the viaduct of three parts. Viaduct as a single column or double-column single frame bridge
Bridge length of 693.607m; surface roads for the road reconstruction project, that section of Plum Road ~ Air Force Hospital expand to 50m, sand
Rivers Bridge widening accordingly; drainage works, including rainwater and sewage pipes.
First, the quality policy
Careful construction, high quality, broaden technology to maintain our edge, dedicated service, customer satisfaction
Second, the scope of quality plan
The quality program is only available within the loop radiation Huangpu Road 2 Lot project.
Third, the project quality objectives
Implementation of total quality management, project time into a good, creative model works fine. Quality of the project to:
1, sub-projects 100% pass rate, good rate of 95%;
2, unit completion of good quality;
3, no quality problems create works to prevent a major quality problems.
Fourth, the principle of quality control
1, adhere to the "hundred years, quality first" principle.
2 people-oriented, as the control of man power, and arouse people's enthusiasm and creativity, and enhance the sense of responsibility empty, tree
Establishment of "quality first" concept to improve the quality of people, to avoid human error, people's work quality and quality assurance processes
Project quality.
3, prevention: the post of quality inspection, to advance the quality control, to check on the quality of engineering products
Investigation, to check on the quality of work, engineering product quality inspection and intermediate
帮助 收藏 报错 评论>> |
本类栏目导航
总点击排行
- 天正建筑2013最新64位破解版
- 160791次
- Autocad2013 64位32位破解版附带注册机
- 148387次
- 天正建筑8.5破解版
- 144090次
- autocad2012 64位32位 破解版(附注册
- 137477次
- 天正建筑8.2破解版
- 123426次
- autocad2010免费下载(简体中文版)
- 97157次
- CAD2008注册机及使用说明
- 80847次
- 免费农村房屋设计图
- 73857次
- cad图集大全
- 56940次
- 11g101图集全套下载
- 45671次
- 公路工程工程质量鉴定报告样板
- 600次
- 土方路基填筑试验段施工总结报告
- 407次
- 1027新华路项目定位报告(含产品建议)11
- 400次
- ***援外公路修复工程质量评估报告
- 398次
- 卓越:成都中天世纪地铁物业城北HOPSCA
- 390次
- 2011年中国双桥长盖板项目市场投资调研
- 383次
- 宁波***区道路、箱涵工程监理工作总结
- 382次
- 关于请求批准开发南谯区双桥门旅游度假
- 381次
- 隧洞洞内爆破观察报告
- 374次
- 中国公路运输行业分析报告
- 373次