合同管理与索赔案例49例.doc
合同管理与索赔案例(一)
《案例1》某建筑工程采用邀请招标方式。业主在招标文件中要求: (1)项目在21个月内完成, (2)采用固定总价合同, (3)无调价条款。承包商投标报价364000美元,工期24个月。在投标书中承包商使用保留条款,要求取消固定价格条款,采用浮动价格。但业主在未同承包商谈判的情况下发出中标函,同时指出:(1) 经审核发现投标书中有计算错误,共多算了7730美元。业主要求在合同总价中减去这个差额,将报价改为356270(即364000-7730)美元。(2) 同意24个月工期。(3) 坚持采用固定价格。承包商答复为: (1)如业主坚持固定价格条款,则承包商在原报价的基础上再增加75000美元。 (2)既然为固定总价合同,则总价优先,计算错误7730美元不应从总价中减去。则合同总价应为439000(即364000+75000)美元。在工程中由于工程变更,使合同工程量又增加了70863美元。工程最终在24个月内完成。最终结算,业主坚持按照改正后的总价356270美元并加上的工程量增加的部分结算,即最终合同总价为427133美元。而承包商坚持总结算价款为509863(即364000+75000+70863)美元。最终经中间人调解,业主接受承包商的要求。案例分析: (1)对承包商保留条款,业主可以在招标文件,或合同条件中规
Contract Management and Claim Case (1)
"Case 1" of a building by inviting tender. Owners in the tender document requirements: (1) project in 21 months, (2) the fixed-price contract, (3) No price adjustment clause. Contractors bidding 364,000 U.S. dollars, period of 24 months. In the tender the contractor to use reservations to cancel the fixed-price terms, with floating prices. But the owner is not the case negotiated with the contractor issued a Letter of Acceptance, also pointed out that: (1) The audit revealed an error in calculating tenders, a total of 7,730 U.S. dollars more than forget. Owners requested the total contract price less the difference will offer to 356,270 (that is, 364000-7730) dollars. (2) agree to 24 months duration. (3) insist on a fixed price. Contractor responses are: (1) A landlord who insist on fixed price terms, the Contractor based on the original offer an additional 75,000 U.S. dollars. (2) Since the fixed price contract, the total price first, calculate the error 7730 U.S. dollars should not be subtracted from the total. The contract price should be 439,000 (ie 364 000 +75000) dollars. As the project changes in the project to contract works added 70,863 U.S. dollars. Projects will be completed in 24 months. Final settlement, the owners insist on in accordance with the correct total amount of 356,270 U.S. dollars after the project, plus additional part of the settlement amount, or the final contract price was 427,133 U.S. dollars. The contractors insist on total settlement price for the 509,863 (or 364 000 +75000 +70863) dollars. Final mediation by intermediary, the owner accepted the request of the contractor. Case study: (1) contractor reservations, owners in the tender document, regulation or contract conditions
帮助中心 收藏 >>> |
本类栏目导航
总点击排行
- 天正建筑2013最新64位破解版
- 173549次
- Autocad2013 64位32位破解版附带注册机
- 154872次
- 天正建筑8.5破解版
- 146385次
- autocad2012 64位32位 破解版(附注册
- 139021次
- 天正建筑8.2破解版
- 127265次
- autocad2010免费下载(简体中文版)
- 98144次
- 免费农村房屋设计图
- 90905次
- CAD2008注册机及使用说明
- 84340次
- 11g101图集全套下载
- 78882次
- cad图集大全
- 67445次
- 项目开工仪式上的讲话稿
- 7911次
- 总工程师岗位职责
- 5616次
- 项目部管理制度汇编
- 2290次
- 钢筋班组劳务分包合同
- 2066次
- 低值易耗品管理制度
- 1498次
- 工程部管理制度
- 1492次
- 钢筋工承包合同
- 1233次
- 财务印章管理制度
- 1071次
- 公司安全专项施工方案专家论证审查制度
- 964次
- 晴雨表
- 962次